Installing an Axis P5655-E with a Louroe Verifact A
Contents
Wiring Diagram
Select Optional Second Camera
Required Parts And Tools
- Axis P5655
- AXIS T94A02L Recessed Mount (If mounting to drop ceiling)
- 3.5mm (Male to Male) Audio Cable
- Louroe Verifact A Microphone
- Axis MultiCable C I/O Audio & Power
- Axis Push-Pull connector
- T20 security bit
- Wire Stripper
- Tap-Cons (if mounting to concrete) (3/16")
- Screws and Anchors (3/16")
- Toggle Bolts (If mounting to drop ceiling tile) (3/16")
- Drill bit and drill
- Phillips head drill bit or Phillips head screwdriver
- Small Flat head screwdriver (#3)
- Shielded Stranded 22/2 + ground Wire
- Razor / box cutter
- B-Connectors
Installation Instructions
Mounting the Camera
- Locate the network drop above the ceiling either being a male Ethernet end (service loop) or a biscuit jack. This will have been ran back to the POE switch.
- Note: If the switch does not have POE, a POE injector will need to be installed at the network closet.
- Remove Axis T94A02L kit from packaging. This will include the mounting bracket and the camera dome ring.
- Determine the location where the 5655 will be mounted and remove the ceiling tile
- Measuring the ceiling mount bracket, note that there is a slight lip to the camera mount
- Find center of the ceiling tile and using a pencil, draw a circle approximately nine inches in diameter
- Using a drywall saw, cut out the section of ceiling tile where the mount will be inserted
- Using a T20 bit, tighten the mounting arms of the ceiling mount
- Pass the Axis MultiCable C I/O and the Ethernet cable through the hole at the top of the camera mount
- Connect cables to their respective ports
- Before locking the 5635 to the mounting posts in the ceiling mount, ensure that the safety cable is attached to the camera
- Insert the camera into the ceiling mount and twist until locked in place securely
- Using a T20 bit, secure the dome ring to the camera mount
- Carefully return the ceiling tile to its location
Note: If not using drop ceiling, use alternate instructions inside of the box for mounting to a hard ceiling.
Connecting Wiring
- Begin but cutting two lengths of 22/2. Ensure they are long enough to reach the microphone location. One will be for audio signal. One will be for power.
- Strip the jacket off the 22/2, revealing the red, black, and common (bare wire) on both sides of the cable.
- Remove the string and plastic casings covering the red and black cables.
- Strip the red and black jackets off the wire exposing the copper. Cut copper evenly on both ends. Remove ground.
- At the Axis MultiCable C I/O, connect the ends of 22/2
- Audio will be connected to the "In" on the audio terminal block - Red to +, Black to -
- Power will be connected to the I/O terminal block - Red to to 2, Black to 1
Connecting the Microphone
- Mark center of the ceiling tile the Verifact A will be mounted on.
- Using a hole saw, drill a hole at center of the ceiling tile. Feed one end of the the 22/2 cables through the hole.
- Strip the jacket off the 22/2, revealing the red, black, and common (bare wire) on both sides of the cable.
- Remove the string and plastic casings covering the red and black cables.
- Strip the red and black jackets off the wire exposing the copper. Cut copper evenly on both ends. Remove ground.
- At the Verifact A, connect the power cable to ports A and C. Connect the audio cable to ports B and C.
- Using toggle bolts, secure the microphone.